As a large-scale outdoor signage product, monument signage is often installed in outdoor public environments, so its quality and safety performance are important factors. Generally, the main structure material of monument signage is mostly welded with metals such as stainless steel and galvanized square pipes. Therefore, the structural welding process of monument signage has become an important factor in determining the service life and quality of monument signage. The following are the specific specifications and standards for the welding process of monument signage.


monument signage


 1. Monument signage structure welding;


Welding process flow: Preparation before welding—Welding—Process requirements—Inspection.


2. Preparation work before welding of monument signage structure;


  3. Read the drawings and technical requirements clearly, and check that the incoming materials are correct before processing;


4. Prepare tools and protective equipment, and check whether the welding machine is well grounded;


5. Remove dirt within 50mm on both sides of the welding edge of the part and keep it straight. Flatness should not be greater than 15% of the thickness of the part;


6. Inspect and measure the fixture before processing;


7. Monument signage welding;


1) Place the workpiece in the exact position according to the drawing requirements. After passing the measurement, spot weld and fix it before welding;


2) Try to use flat welding when welding. If welding in other positions, the welding current should be adjusted to be 10% less than the flat welding current;


3) During the welding process, the dimensions must be measured at any time to see if they meet the requirements to prevent deformation;


4) When the weld is long or the structure is assembled, it should be fixed by spot welding in sections and then welded to avoid deformation;


5) When welding the hinge on the cover, the cover should be padded by 2~3mm and welded with a hinge fixture to ensure flexible door opening and closing and sufficient mechanical strength. The width of the door gap shall not be greater than 2mm, and the opening angle of the door shall not be less than 90°;


6) The arc crater should be filled when closing the arc, and the arc crater should not exceed 5mm;


7) After welding, remove the coating and clean the welding nodules and slag to ensure the weld is smooth and clean;


8) Technical requirements should be met during welding to ensure welding strength;


9) After molding, the appearance should be adjusted accordingly according to the drawing requirements and standards.


8. Process requirements;


1) Local deformation caused by welding shall not be caused and shall be smoothed;


2) Welding is not allowed on non-welding parts, fixtures and welding platforms;


3) The parts and cover parts that require corner sealing are sealed with gas welding, and they should be rounded after welding;


4) The allowable deviations of overall dimensions and verticality are in accordance with relevant regulations;


5) The same gap or parallel gap formed between structural elements on the surface of the structure should be uniform;


6) The general tolerance for flatness of panels, side panels, door panels and other panel components is less than 3mm for any square meter, and panels are usually less than 1.5mm;


7) The grounding device should be fully welded around it and the connecting threads should not be damaged.


9. Inspection;


1) The shape, size and position of the weld should meet the technical requirements;


2) The appearance of the welding joint shall not have defects such as undercuts, lack of fusion, burn-through, welding nodules and missing welds; it shall also not have defects such as slag inclusions, pores and cracks.


10. Polishing and testing;


    After welding, the workpiece should be properly polished to make the component smooth and uniform, without missing welds, cracks, slag spatter, burrs, etc. The processed parts that have passed the above process will be comprehensively inspected according to technical specifications. Only after passing the inspection can they be transferred to the next process.


Monument signage materials are diverse. Not all monument signage s are made of metal, and not all monument signage production requires welding processes.

Hunan Aiaoni Signage Engineering Co., Ltd. has 15 years of experience in signage design and more than 100 professional production teams,Phone:139-7318-3738,Website:www.hnaan.cn

Share:
Back to List
Previous: What kind of design skills does monument signage have? Next: What kind of functions does signage design have?

Recommended articles

Hunan Aiaoni Signage Engineering Co., Ltd.

Telephone:

Email:372405779@qq.com

Mobile: 139-7318-3738

Hunan Aiaoni Signage Engineering Co., Ltd.  Hunan ICP No. 17021931  Address: No. 316, 3rd Floor, Building 2, Haipingyuan, No. 229 Guyuan Road, Changsha High-tech Development Zone

Copyright © 2014-2026Hunan Aiaoni Signage Engineering Co., Ltd.

简体中文